MCCo Construction Projects
Ireland Cancer Hospital Utility Project
- Install 36-inch diameter supply and return chilled water lines from satellite chilled water plant to Ireland Cancer Hospital via Cornell Road
- Project also includes installation of a 20-inch steam line and 11.47 kV electrical feeder to serve the new cancer hospital
- Projected Completion May 2010
MCCo Powerhouse - New Gas Boiler
- Installation of a new natural gas fired 100,000 pound per hour package boiler
- Demolition of 2 boilers (decommissoned in 1999) completed in September 2009
- Bid for new boiler construction to be awarded mid-January 2010
- Boiler installation anticipated to begin October 2010
- Projected Completion May 2011
MCCo 138kV Substation Expansion
- Expansion of the existing substation to serve future needs of new Chilled Water Plant addition
- Secondary switchgear equipment to be installed in June 2010
- Cable pull from substation to new CWP site anticipated for late 2010
- Projected Completion End of 2010
Chilled Water Plant Expansion
- Additional Capacity at Existing Plant
- Addition of (2) 2,000-ton chillers to existing Satellite CWP
- Bids due January 15th, 2010
- Installation expected to occur in Fall 2010
- Projected Completion Late 2010
New Satellite Chilled Water Plant Building
- Bids due March 2010
- Letter of Intent for (2) 2,200-ton chillers and cooling tower has been issued
- Permit-to-Install for cooling tower has been received